Eumseong Combined Power Plant Cooling Tower Project, Eumseong-gun, Chungcheongbuk-do, South Korea

  • épülettípus:
  • energetikai szerkezetek
teljes képernyő bezárás

This project marks Peikko’s third cooling tower project in Korea, and it holds particular significance as a public-sector project.

One of the key benefits of applying Peikko’s solution to this project was the remarkable speed of installation. By combining precast concrete construction with Peikko’s innovative connection systems, the overall construction period was reduced by more than two months compared to traditional cast-in-place methods. Moreover, the entire project was completed without any safety incidents.

The site was visited by representatives from universities, corporations, and public institutions, all of whom gave positive feedback on Peikko’s dry joint solution for precast concrete. This project clearly demonstrates how Peikko’s technology can enhance both efficiency and safety in modern construction.

bővebben down-arrow.png

projekt adatok

projekt mérete:
10 cooling towers m2
fejlesztő:
KOREA EAST-WEST POWER CO.,LTD
kivitelező cég:
POSCO E&C
szerkezettervező:
RISE STRUCTURAL ENGINEERING
építész:
TAEHWA ENGINEERING CO., LTD (SHOP DESIGN)
előregyártó:
KOREA OCEAN PLATFORM CO.,LTD
szállítás éve:
2023~2024
átadás éve:
2024

Kapcsolat