Capella Laboratory, Cambridge, UK

  • épülettípus:
  • oktatási és kulturális épületek
teljes képernyő bezárás

A new laboratory for Cambridge University based on the Addenbrooks Hospital site.

Featuring 489nr DELTABEAM® @ 2.75km, the design required very low response factors due to sensitive lab equipment.

The origional cast in-situ design was for a 700mm deep slab but after a lot of work it was shown that D32-500 DELTABEAM® Composite Beams along with 300mm deep hollowcore with a 200mm structural topping would meet the vibration performance specfication.

DELTABEAM® along with other offsite methods allowed the construction time to be 20 weeks faster and reduced over 500 truck deliveries when compared to the cast in-situ solution.  

bővebben down-arrow.png

Our onsite construction program was 20 weeks faster and saved over 2,500 man weeks in comparison with the envisaged in-situ solution. Additionally the overall carbon footprint was significantly reduced with fewer truck deliveries and high quality offsite production of the steel Deltabeams and precast concrete units

Nickie Brown, Managing Director PCE Ltd

projekt adatok

projekt mérete:
17,000 m2
szintszám:
7
kivitelező cég:
PCE Ltd
szerkezettervező:
ARUP
építész:
Fairhurst Design Group
szállítás éve:
2016
átadás éve:
2017